The works of Itaquerão reached 34.6% of execution in the last Monday (May 7th), according to statement released by the construction company Odebrecht, responsible for the work.
At this time, all the 1,710 workers finish the pile driving for the stadium foundations. The assembly of the east and south bleachers has already begun.
In addition to 3,650 driven piles, 252 columns, 339 beams, 146 raker beams, 2146 slabs and 688 steps have already been assembled.
The west section is also under construction at Itaquerão, where there is the construction of a retaining wall to separate the building from one of the open parking lots.