To speed up work rhythm, employees shall be moonlighting at Itaquerão

Work on the stadium due to open the World Cup shall have a new shift, from 8 p.m. to 5:40 a.m.

The new Corinthians Stadium is almost 23% completed (credit: Odebrecht/Publicity)
Font size
From the Editorial Staff - São Paulo
Posted on 04/01/2012 15:17 h
updated on 17/01/2012 13:02 h

Within 15 days, Odebrecht, the construction firm responsible for the construction of the Itaquerão, shall open a third working shift on the work site of the stadium due to receive the opening match of the 2014 World Cup. The information was provided by the “UOL” web portal.

The construction company shall take on 60 new employees who shall work through the night, from 8 p.m. to 5:40 a.m. In October 2011, the night shift, from 3 p.m. to 11:30 p.m., had already been started.

Together with the initial working hours from 7:30 a.m. to 6:30 p.m., now this work site shall have almost 24 hours of work a day, all of this being so that the Corinthians Arena can be ready by December 2013.

At the moment, 23% of the work on this project have been completed.





 
our team
production
Sinaenco - Sindicato Nacional das Empresas de Arquitetura e Engenharia Consultiva
technology and creation
XY2 | Agência Digital
hosting
Telium Networks
information security
LSI TEC - Laboratório de Sistemas Integráveis Tecnológico
 
sponsorship
Gerdau
 
support
ArcelorMittal
 
Minimum resolution 1024x768 - © Copyright 2009 portal2014.org.br All rights reserved.